The Frame Arrives

So the day arrived – but the frame didn’t – well not when it was supposed to anyway. The frame was supplied by u-roof based in Yorkshire.  There had been a huge amount of discussion as to how to deliver it. … Continue reading

Posted in general | Leave a comment

The Slab is Complete

Well it has taken 2 weeks from blockwork complete to getting the slab poured.  The rain has been relentless and really slowed us down.  We got to last Friday Morning and Eddie suggested he would have to cancel the concrete … Continue reading

Posted in general | Leave a comment

Started at Last

Well we have started on the plot at last and between rain of Noah’s Ark proportions we have managed to get the Foundations complete.  I bought a time lapse camera a Brino Garden Watch which is good but played up … Continue reading