Wall Complete and Windows Going In

I realised that I had not really done an update on progress.  So where are we? The insulating of the walls were completed week before last and since then the flooring has gone down on the first floor and the … Continue reading

Posted in Selfbuild | 1 Comment

The Windows Arrive

Well the windows and doors from Albo in the Czech Republic are here and we managed to unload them by hand!  They look good I just hope they fit.

Posted in Selfbuild | Leave a comment

Nu-Lok Roofing System

A long time ago I came across the Nu-Lok roofing system. One of the issues was that I could not slate the roof in a traditional way as the sarking layer would pose a major design issue in terms of … Continue reading

Posted in Selfbuild | 2 Comments